A short design and construction schedule …

July 2015

DTT proposal (Blue Book)

July 2015

Apr 2018

Frascati selected as DTT site

End 2018

Launched first call for tender procedure (for SC strands)

End 2018

Apr 2019

DTT Interim Design Report (Green Book)

June 2019

Availability of European Found for Strategic Investments (EFSI) portfolio guarantee to obtain 250 M€ European Investment Bank (EIB) loan

June 2019

Aug 2019

Partial award of SC strand contract

Sept 2019

Establishment of DTT Consortium. 

ENEA and CREATE Consortium first partners.

Sept 2019

2020

ENI joins DTT Consortium

2021

Six new partners join DTT Consortium: INFN, RFX Consortium, Politecnico di Torino, University of Tuscia, University of Milano-Bicocca, Università di Roma Tor-Vergata

2021

2022

Large of the basic machine completed (6 TFCs, 3 VV sectors, cryostat base, main hall, ...)

2022-2023

Decision on divertor configuration (PEX)

2022-2023

2022-2026

Assembly and commissioning

2026

First experimental plasma: 3T, 2 MA

2026

2026- …

Operations

Operational Planning